Archives: May 2015

(28.05.2015) Janajyoti secondary school, Leptung, Dolakha district:

16

Janajyoti Secondary School collapse

 

 

The majority of the villagers have now built their temporary house. Our aim is now to support the construction of a temporary school for the 360 kids of this area. We brought the shelters to built 12 classrooms (452 steel sheets) 5 toilets, the necessary tools, 10 dashboards for each classroom, a notebook and pen/pencil for each kid. Everybody was taking part in the transport of the material from the road till up to the village, from the young kids to the old people. An amazing mixture of generations.
The headmaster is now coordinating with the community of the villagers to start as soon as possible the construction of the temporary school.
We are looking forward to going back in about one week to see the advance of the work with the food to prepare the lunches at school for 1 month for the 360 kids and 12 teachers, together with some playing games material.

A special thank to all of you, and in particular to our friends Jessica Tradati and Séverine Pont Combe (Association les Enfants du Sourire) for their specific support in this temporary school project.

0

rough design of school, 22 feet length, 15 feet wide, 8 feet hight

1

Head teacher of Janajyoti School, estimating the steel sheet per class

2

Villagers happy to carry sheet for school

3

Villagers happy to carry sheet for school

4

Villagers happy to carry sheet for school

5

Villagers happy to carry sheet for school

7

Norbu happy to carry sheet for school

8

Head teacher happy to carry sheet for school

9

Teacher happy to carry sheet for school

10

brooken school bench

11

teacher showing the attendance copy

12

Villagers happy to carry sheet for school

13

Andrea happy to carry sheet for school

14

Collapse school toilet

15

collapse janajyoti Secondary school

16

collapse janajyoti Secondary school

 

27.05.2015 Leptung village, Second visit

29

The first time Norbu and me were supposed to go to this village was on 12 May 2015 but we were stopped in the middle of our way and very close to the epicentre by the second massive earthquake. Fortunately, the food could still be brought at destination several days later by the head teacher of such village (see article from 13 May 2015).

This time, we started from Kathmandu with a strange feeling in our stomach and “our survival bag”, just in case… As we came closer to the last epicentre area, some big rocks at the road side remind us of our last trip and we could see that the local people are now courageously under the heat demolishing some parts of their houses to built their temporary houses before the coming monsoon.
After 7 hours driving and a stop in the district town, Charikot, which has been severely affected by the second earthquake, we arrived at destination. It was already dark and too late to call the villagers to get the food that we brought with us.
A 5 o’clock wake-up by the roaster and everybody was ready and excited to see what they would receive this time. The headmaster invited the 109 families that did not receive food till now to come to the distribution point, together with the other villagers to get the shelters for the school.

0 1 2 6 8 9 10 11 12 13 14 15 16 17 18 19 20 21 23 24 25 26 28 29 30 31

 

Some news from Nepal one month after the tragic earthquake

Kathmandu and around
– Airport: Nepal can be reached by the airs: Tribhuvan Airport, international and national, has not been damaged. Army and private helicopters are still daily very busy by providing supplies and help in the different remote affected areas too.
– Hotels and restaurants: the majority of the touristic hotels are open and have announced that they are operational and ready for the next season, which starts at the beginning of the coming Autumn 2015. The situation is similar for the restaurants.
– Transportation means: as well the taxis as the various other transportation means are operational;
– Roads: a very few roads have been damaged by the recent earthquakes, but the workers are already rebuilding them as where it is necessary.
– UNESCO Heritage sites: 3 of 10 are damaged, but it is now one of the Government’s priority to approve the budget for their re-affectation. It has also foreseen to present to the public large pictures of the monuments that need to be rebuilt on the different sites.
– Thamel: the most touristic part of Kathmandu, seems to be lost without its usual tourists at that time of the year…Most of the small and overloaded colourful shops are open but the clients are only few;
– Shops: the majority of them have reopened a few days after each earthquakes.
– Private buildings: as shown by the media too, some private buildings have either collapsed or are threatening to collapse, or are more or less damaged.
– Local population: there are still some people sleeping outside in their tents, whereas daily life comes slowly back to normality.
– Wild animals: people in the village of Bhaktapur district, situated in the lower land at one-hour drive more Kathmandu have to spend nights amid fears of wild beast (leopards) and snakes while they sleep in tents after their houses collapsed or were damaged in the devastating recent earthquakes of 25 April and 12 May 2015.
Affected regions
– Districts: More than 29 districts of 75 districts have been affected by the 25 April earthquake, mainly situated in the hills regions of Nepal. The district of Sindulpalchhowk where we have been at the time of this earthquake being one of the most affected. More than 3400 deaths are registered, all 557 schools and 52 health post buildings of this district have been razed to the ground in the quake, suspended bridges have collapsed among other (and this is just the example of one of the affected regions…). In some parts drinking water is getting a problem too and some villages till today were almost not, if not supplied.
– Migrants: Nepali migrants return to quake epicentre to rebuilt their villages stone by stone as this 30 year old Nepali who put off the promise of a job in Japan to return to the rubble of his childhood home: “I came back to rebuilt and to help my mother”.
– Dangers: access roads are threatened by landslides and rock falls due to the massive earthquakes and recurring aftershocks. Rocks and soil in the hills have lost rigidity making landslides a common occurence, that are for this period of the year uncommon and, which will increase during the coming monsoon.
– Relocation: some of the villages that are considered as being under high risk and vulnerable to earthquakes are relocated/resettled. For example, Tatopani the village in which Norbu and me were blocked on our way to Mount Everest on 25 April 2015, is resettled in the middle of Kathmandu in a field nearby we live. Under the heat of Kathmandu, they try to arrange at their best their tented provisory “new village”. Some of them have never been before in the capital but they have no other choice, but all worry about their future.
– Women: women are particularly facing difficult situations after these recent earthquakes; numerous of them have given birth, as the woman we saw in Tatopani, in the middle of the nature, under a tent or a shelter, but in the majority of the cases in precarious conditions and with no means or no where to go in case of complication due the stressful situation of the earthquake experience and others];
– Loss: besides the tragic human loss reaching more that 8600 casualties till today, the villagers of the affected regions that are mostly farmers in remote parts of Nepal, living with less means, have to take on them the loss of most of their cattle and tonnes of food stocked in their houses that have collapsed. Almost every family of such regions owns a few animals (goats, buffalo, cows, yak, chicken) that represents an important fortune, or the only real fortune, for most of them. The animals are often tightened under a cover besides the houses. The food consist mainly, but depending the regions and the altitude, of paddy, maize, wheat, buckwheat, pulses, spices, potatoes along with the seeds. And at this date, still some people are missing.

Tourismus
– Income: an important part of the national revenue for Nepal comes from the tourism sector, among others through the entry fees to the monuments, the trekking and climbing permits of the different national conservation areas. Considering the usual two “high seasons” for Nepal, namely Spring (March to May) and Autumn (September to mid-December), and the fact that the Spring 2015 season was prematurely over after 25 April, Nepal works now hard to make its possible that the next season is not in a total deficit again. Income generated by the tourists visiting Nepal would also at the same time help for the reconstruction of the damaged parts of some of the Heritage sites. According to what one can see now, most of the capital, Kathmandu, will be worth and safe enough for visiting in the coming Autumn.
– Affected population: from the personal welcoming the guests at Kathmandu Tribhuvan international airport, the luggage porters, the taxi drivers, hotels, restaurants, lodges, the touristic and mountain guides, the climbing sherpas, the food suppliers, trekking porters to the shops owners in the touristic areas all are seriously affected by this disaster. This means in other words that no income at all is flossing in that would permit them to rebuilt their houses, shops or else. Furthermore, there is no contribution for un-employment in Nepal and the insurance money, if any, does not help a lot for does who have to rebuilt their houses.
– Change of Nepal Tourism ministry: the recent nomination of a Sherpa (Kripasur Sherpa) as new Tourism ministry for Nepal is seen to be construed as a meaningful move as he is close to some key institutions in the tourism sector.
– Current situation: Kathmandu, as said above, the city is safe enough and the majority of the hotels, restaurants and sightseeing places are accessible. The trekking/expedition regions, some of the regions have been affected a lot, while others have not been affected at all; it therefore possible to plan a trip to Nepal already for the coming Autumn but with clear information from your agency about where to go.

Government
– Casualties: according to the data on human casualties of the 25 earthquakes and the numerous subsequent aftershocks made public by the Nepali Police, women deaths have outnumbered the men deaths. According to some gender experts, traditional role of women could be one of the reasons behind more women losing lives in such disasters. Especially, in countries as Nepal, where unfortunately the rate of uneducated women is still very high. One more reason for us, to support the kids’ education as best as we can through our Butterfly Help Project (www.butterflyhelpproject.org).
– Building assessment: the Nepal government, though a team of experts of its Department of Urban Development and Building Construction (DUDBC), is preparing to re-assess all housing apartments in Kathmandu Valley after the recent powerful earthquakes. Three categories of buildings are made: i) unsafe, ii) safe to stay and, iii) need of some maintenance. The assessment is done in two parts, first based on visual assessment, then on a detailed inspection. But their is an urgent need of additional engineers…there are only 400 structural engineers in Nepal. It results in having several thousand people that are still languishing in makeshift shelters as they have not found an engineer for consultation about the safety of their houses.
– Buildings demolition: Government lacks equipment to demolish multi-storey buildings; due to the lack of technical knowledge and machines to demolish broken houses threatening others by the governement, some of the owners have taken their own initiative because of the danger for the neighbourhood. The government has issued a circular that house owners will get relief as per the policy even if they demolish the structures themselves. However, it seems that the decision on how the government will financially assist homeowners who demolish their houses on their own has not been published yet, many people are hesitant even though it poses a risk to others. According to the Deputy Commissioner at Kathmandu Valley “It is a matter of shame that the government is passive about this. It lacks manpower and technology to demolish structures. The government own two 22 tonnes and two 12 tonnes cranes. There is no policy and plan to use mild explosion to demolish structures inside the alleys and stories above five.” Such statement is confirmed by the Secretary at the Ministry of Urban Development “obviously it is time consuming, while the government lacks resources, manpower and expertise. The government has no technology and equipment to demolish structures behind five-storey buildings. The government is asking for assistance from neighbouring countries and is encouraging homeowners to demolish structures themselves as they can save and reuse construction materials.” It seems that till to date the government has demolished 150 houses with the assistance from the District Administration Office, Nepal Army, Nepal Police and Nepal Armed Force.
– Reconstruction plan: one of the main suggestion that should be an integral part of future disaster preparedness and management planning according to the population of Kathmandu is to increase the open spaces in the Kathmandu Valley. Earthquake resistance construction, strict enforcement of building codes, zoning laws and open spaces are the key dimensions to improve the process of assessing the emergency preparedness as stated in the media by a Senior economist at the Institute for Intergrated Development Studies.
the Himalaya due to its situation in the middle of the two continental tectonic plates (Eurasia and Indian) being naturally exposed to such risk, then in case of fire and other natural disasters. “Unplanned physical structures are the major cause of the large number of death toll. It is therefore extremely important for the government to make and formulate strict national building code” as stated by the media.
– Relief money: the Government has decided to allocate USD 360 for and USD 400 not yet distributed.
– Geological survey: the Government has recently planned to conduct a geological survey of 6 earthquake affected districts with 18 task forces of geologists. The teams chosen for such survey will base their study on field surveys and satellite data. The aim is that the geological report submitted by the task forces would help the Government to relocate human settlements of the areas rattled by the earthquake and give exact number of human settlements affected by the earthquake in order to help to plan the resettlement of the affected people, together with an assessment of the risks of landslides in such areas.
– Schools: according to the Department of Education, around 30,000 classrooms and 3,550 school buildings in 45 districts, including in the Kathmandu Valley, were damaged by the earthquakes and aftershocks. Parents are want now schools to resume as a dad says “Had the children started going to the school from May 14, things would have fallen in place, as they would have got time to play and interact with friends which would have helped them forget the disaster.” After the 25 April quake, the government had announced closure of the schools and said that classes would resume from May 14. But following to the 12 May quake, the government said the schools would remain close for another two weeks. Schools are now due to open on May 31. Even some of the students seem more and more missing going to school: a 16-year young girl of the Gorkha region (near to the Mount Manaslu, 8163 meters) explains that one part of her school has collapsed and some other parts were damaged, which render it not safe enough to resume school in its original buildings, and furthermore she is daily busy in fetching mud to help her parents rebuild their family house, but “I miss going to school. I always liked getting up in the morning and helping my parents in doing household chores before heading for school. It always felt good to learn new things from our teachers”.

Sport
– Stadiums as campsites: “A revered national sports coach is among the thousands of dead, trapped in his rented house when devasting earthquakes rocked Nepal. The main football stadium was damaged, before becoming a makeshift refuge for displaced survivors of the quakes. The national cricket team’s preparations for a major international tournament next are in disarray. The Asian weightlifting championships, schduled for Kathmandu in July, are destined to be held somewhere else.” (Repubica / International New York Times, 20 May 2015).
– Sport as new energy: despite this tragic situation, people are enccouraged by the National Olympic Committee of Nepal to turn their attention back to sport to help them to overcome traumatic experiences. According to the Head of the Nepal National Olympic Committee “Our primary focus is to create a healthy environment for athletes. We are planning to distribute sports kits at earthquake hit areas since we believe sports to be the best tool to restore normalcy.”
– Testimony of a young Nepali high-level athlete: a few days ago, there was an article in the Nepal media about a 12-year old Nepali girl competing in swimming, who is now residing and training hard in London, UK. She has set her eyes high, at the next FINA World Championships, Asian Games and the Olympic Games. Her testimony is touching: “My father is helping people heal (in Nepal) using his skills as a doctor. I want to use my skills as a swimmer to give some hope and happiness by doing well in the FINA World Championships.” She was in Nepal at the time of the first earthquake of 25 April 2015 as she came to participate in the 20th National Swimming Championship.

As a conclusion, to help Nepal is not only during the close period after these earthquakes, but to help Nepal has to go on for years and one of the main support is to come back to Nepal from the next season, namely this Autumn. This will permit Nepal and the numerous people living from the tourism income to go on with the rebuilding of their country.
Finally, we adress a special thought to all these families that have lost one of theirs and those who need now to rebuild their losses.

THANK YOU FOR YOUR PRECIOUS SUPPORT!

0 1 2 311063505_471371726345457_2009222178847603126_n
Sources:
– Testimonies of Norbu’s friends and others
– the Kathmandu Post
– the Himalayan Times

The villagers are getting stronger

20 May 2015: under a strong morning heat, we start from Kathmandu to go back to this small hilly village, which is situated in one of the most affected district, Sindulpalchok-3. Our small truck is loaded with food supplies again, steel shelters and material (hammers, nails, shovels, iron wire, etc.) for the families of this small village to build temporary shelters that are stronger than the tents to pass the coming monsoon.
At our arrival, we are happy to see that despite the great heat and difficult life conditions, the people are working hard on divising and recovering small pieces of their broken houses for the new ones.

We are really happy that we could provide them at least with some of the vital means that give them a basis to reconstruct slowly but surely their lifes. While we were there for the second time we could see that these families are now strong enough to think of their own to go on.

We have still now many villages to encourage and check what they did during this laps of time since our first venue.

0 1 2 3 4 5 6 7 8 9 10 11 12 13

The porters’ village

IMG_2517

19th May 2015: One week after the second big earthquake that has strongly affected Nepal again, we have started early this morning to go to Rusawa district situated in the Langtang national park area at about 5 hours of driving from Kathamndu. Further to this recent earthquake it was necessary to let the earth slightly calm down before going in this kind of places.

The road is not too bad until a few kilometers before our destination.
Until today only very few supplies arrived since 25 April 2015 till the village we go.
It is situated at about 45 kilometers before the Tibet border on a very steep mountain flank at 2300 meters. Mostly porters of the Tamang ethical group that are hired during the trekking seasons live there with their families. Their villages is destroyed, 21 people lost their life and the current trekking season is already over.
It takes us a while to provide more than 5 tons of food that is divided into the 136 families living there. The people from the village are calmly sitting watching the preparation of the different ratios of food. What a scene…kids, moms with small babies, teenagers, older, everybody is there as if it would be market day.
Happy, we drive back to Kathmandu, the mind full of beautiful smiles.

Thank you to all of you for your generous contributions that permit to render a smile to these people living already before the tragic earthquakes with very less means.
Our support can go on thanks to you!

10243123Ramche1361014356776783123455

 

Trapped again…

Trapped again…

12 May 2015: With the aim to bring an additional load of food of more than 2 tons to the remote village of Leptung in the Dolakha district combined with an observation trip to the Janajyoti secondary school, we leave Kathmandu in the early morning. An 8 to 9-hour trip of 185 km expects us. The first part, we take the same road that a few weeks before when we started from Kathmandu to go to the Tibetan border for our expeditions…strange feeling.
Due to the earthquake of 25 April 2015, the Chinese mountaineering associations that are competent to deliver the climbing permits have decided to stop all expeditions for this season.
After more than 120 km, we stop in a small village for a short lunch break. The local people of that village are busy in trying to find some of their belongings in the middle of their collapsed houses, or in collecting the remain wood and other useful parts of their broken house that they might use to rebuilt the new one before the coming monsoon.
Everything happens suddenly so quickly…
A strong noise, lots of dust and the road flotting in the air…it is almost impossible to run away the feeling of staying on waves being so strong…And where to run again, the dust of some further parts of houses that just collapsed besides us avoids us to see clearly if something else could fall down on our heads…The local people being in total panic, we are surrounded by screams until the shakes stop for a while but before the two big next earthaquakes…The communication tower gets into fire, the phone connection cracks down…Helicopters are suddenly flying above us, whereas injuried people are still around us.
In total we are experiencing three strong earthquakes (magnitude of 7.3, 6.4 and 5.8), in the middle of their epicentres.
We do not take the risk to check whether and when the roads is cleared up, since some landslides and permanent rock fallings continue to happen due to the numerous aftershakes. We can reach a plateau at 2850 mètres above sea level (that would be so beautiful in normal circumstances) and settle the tents we have with us for the night. We are lucky to eat some local food among other people who remain at the same place as us.
13 May: Early in the morning, we hear that thanks to the local people who still have the courage to carry on, assisted by some international help troups that came to Nepal after the first earthquake of 25 April 2015, the main road to Kathmandu is now open again. The road to go to our destination remains however blocked.
We are lucky that we can manage to handhover our loads to the headteacher of the school where we were supposed to go. He will be in charge to provide us with a report of the distribution among the village people.
On our way back to Kathmandu, we observe the destruction of some houses that where in a good shape on our way up and scary landslides/rock falling that are still blocking the road in some of its parts.
What an adventure!
People are again sleeping outside in Kathmandu, as we will do again…But most of the Nepali try as soon after the shock has passed to react and go on with the reconstruction of their houses.
Dolaka0 Dolaka1 Dolaka2 Dolaka3 Dolaka4 Dolaka5 Dolaka6 Dolaka7 Dolaka8 Dolaka9 Dolaka10 Dolaka11 Dolaka12 Dolaka13 Dolaka14 Dolaka15 Dolaka16 Dolaka17 Dolaka18 Dolaka19 Dolaka20 Dolaka21 Dolaka22 Dolaka23 Dolaka24 Dolaka25 Dolaka26 Dolaka27 Dolaka28 Dolaka29 Dolaka30